The significant events and conditions affecting TransAlta?s business during the
last three financial years are summarized below. A number of these events and
conditions are discussed in greater detail under the heading ?Business of
TransAlta? in this Annual Information Form.
Year-ended December 31, 2003
? On December 10, 2003, Vision Quest Windelectric Inc. (?Vision Quest?), which
was then a wholly-owned subsidiary of the Corporation, received Alberta
Energy and Utilities Board (the ?EUB?) approval to begin construction of the
$95 million Summerview 68-MW wind farm located approximately 15 kilometres
northeast of Pincher Creek, Alberta. The Summerview facility, to be
comprised of 38 1.8 MW turbines, is expected to be completed in mid-2004 and
will bring Vision Quest?s total operated capacity to approximately 190 MW. ...